Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | KLSR - RAYS (JV) | 20086048 | KHARARGADI GRAM PANCHAYAT WATER SUPPLY SCHEME | 216.61 | 120.52 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 10249.00 | 9756.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ratanpura | Kharargadi | 465823 | Kharargadi | 185 | 185 | 100 | Har Gar Jal | Certified |
| 2 | Mau | Ratanpura | Kharargadi | 465824 | Turk Gandava | 70 | 70 | 100 | Har Gar Jal | Not Certified |
| 3 | Mau | Ratanpura | Kharargadi | 465825 | Malaria | 14 | 14 | 100 | Har Gar Jal | Not Certified |