Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sant Kabeer Nagar
AGENCY VISHVARAJ
SCHEME ID 20086049
SCHEME NAME Karri Khas GP WSS
ESTIMATED COST 484.62
EXPENDITURE 373.19
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 37
Procured 0 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 13233.00 Meter
Length Laid 11817.90 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sant Kabeer Nagar Khalilabad Karri Khas 452618 Karri 510 503 99% Work In Progress Not Certified
2 Sant Kabeer Nagar Khalilabad Karri Khas 452619 Bardand 18 17 94% Work In Progress Not Certified
3 Sant Kabeer Nagar Khalilabad Karri Khas 452620 Paraspur 82 81 99% Work In Progress Not Certified