Scheme Details
DISTRICT
Sant Kabeer Nagar
AGENCY
VISHVARAJ
SCHEME ID
20086151
SCHEME NAME
NAHARDEEH , BHEETI HARDO &PANARAM GOV WSS
ESTIMATED COST
408.59
EXPENDITURE
232.78
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
27
Procured
27
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18804.00
Meter
Length Laid
10082.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Khalilabad | Panaram | 452667 | Panaram | 108 | 108 | 100% | Har Ghar Jal | Not Certified |
| 2 | Sant Kabeer Nagar | Khalilabad | Panaram | 452668 | Bhataura | 57 | 46 | 81% | Work In Progress | Not Certified |
| 3 | Sant Kabeer Nagar | Khalilabad | Nahardeeh | 452670 | Nahardeeh | 157 | 148 | 94% | Work In Progress | Not Certified |
| 4 | Sant Kabeer Nagar | Khalilabad | Bheeti Hardo | 452671 | Bheeti Hardo | 120 | 113 | 94% | Work In Progress | Not Certified |
| 5 | Sant Kabeer Nagar | Khalilabad | Bheeti Hardo | 452672 | Usrapar | 92 | 73 | 79% | Work In Progress | Not Certified |