Scheme Details
DISTRICT
Mau
AGENCY
KLSR - RAYS (JV)
SCHEME ID
20086200
SCHEME NAME
BIJOULI & MAKRI GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
311.70
EXPENDITURE
154.20
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24945.00
Meter
Length Laid
21944.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Muhammadabad Gohana | Makri | 465997 | Makri | 92 | 87 | 95% | Work In Progress | Not Certified |
| 2 | Mau | Muhammadabad Gohana | Makri | 466000 | Fulwaria | 65 | 65 | 100% | Har Ghar Jal | Not Certified |
| 3 | Mau | Muhammadabad Gohana | Makri | 466003 | Kutubpur | 63 | 57 | 90% | Work In Progress | Not Certified |
| 4 | Mau | Muhammadabad Gohana | Bijouli | 466005 | Bairampur | 15 | 4 | 27% | Work In Progress | Not Certified |
| 5 | Mau | Muhammadabad Gohana | Bijouli | 466006 | Bijovli | 131 | 111 | 85% | Work In Progress | Not Certified |
| 6 | Mau | Muhammadabad Gohana | Bijouli | 466007 | Jolhapur | 37 | 23 | 62% | Work In Progress | Not Certified |