Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20086219 | ANAAI WATER SUPPLY SCHEME | 375.63 | 211.81 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 23 | 23 | Yes | 0 | NA | No | 26593.00 | 20727.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Jahanaganj | Anaai | 463135 | Taracha | 87 | 80 | 92 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Jahanaganj | Anaai | 463194 | Chak Tulsi | 33 | 30 | 91 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Jahanaganj | Anaai | 463250 | Anaai | 152 | 147 | 97 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Jahanaganj | Anaai | 463273 | Kadipur | 129 | 127 | 98 | Work In Progress | Not Certified |