Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20086314 | DILLA W/S SCHEME (HFCL) | 217.85 | 77.79 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Jakhania | Dilla | 471525 | Dilla | 145 | 139 | 96 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Jakhania | Dilla | 471526 | Dhaurehra Gopal Rai | 53 | 49 | 92 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Jakhania | Dilla | 471527 | Mirjapur | 62 | 59 | 95 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Jakhania | Dilla | 678268 | Araji Kubarja | 3 | 2 | 67 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | Yes | 0 | NA | No | 5852.00 | 5847.00 |