Scheme Details
DISTRICT
Sant Kabeer Nagar
AGENCY
VISHVARAJ
SCHEME ID
20086321
SCHEME NAME
KISHNUPUR GP WSS
ESTIMATED COST
175.25
EXPENDITURE
80.61
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7101.00
Meter
Length Laid
7484.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Pauli | Kishunpur | 453145 | Kishunpur | 265 | 253 | 95% | Work In Progress | Not Certified |
| 2 | Sant Kabeer Nagar | Pauli | Kishunpur | 453146 | Shewrampur | 1 | 1 | 100% | Har Ghar Jal | Not Certified |
| 3 | Sant Kabeer Nagar | Pauli | Kishunpur | 453147 | Saurahakala | 14 | 1 | 7% | Work In Progress | Not Certified |