Scheme Details
DISTRICT
Sant Kabeer Nagar
AGENCY
VISHVARAJ
SCHEME ID
20086322
SCHEME NAME
MATAULI GP WSS
ESTIMATED COST
189.65
EXPENDITURE
105.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9965.00
Meter
Length Laid
7974.20
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Pauli | Matauli | 453148 | Matauli | 144 | 141 | 98% | Work In Progress | Not Certified |
| 2 | Sant Kabeer Nagar | Pauli | Matauli | 453150 | Mankoopur | 95 | 89 | 94% | Work In Progress | Not Certified |