Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20086398 | RAISPUR W/S SCHEME (HFCL) | 337.95 | 105.47 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | NA | 15 | NA | No | 20426.00 | 12553.01 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Raispur | 472445 | Raispur | 108 | 97 | 90 | Work In Progress | Not Certified | 
| 2 | Ghazipur | Deokali | Raispur | 472446 | Enayatpur | 75 | 67 | 89 | Work In Progress | Not Certified | 
| 3 | Ghazipur | Deokali | Raispur | 472447 | Bhira | 84 | 75 | 89 | Work In Progress | Not Certified | 
| 4 | Ghazipur | Deokali | Raispur | 472448 | Chak Gaus | 37 | 33 | 89 | Work In Progress | Not Certified | 
| 5 | Ghazipur | Deokali | Raispur | 472449 | Neecoat | 46 | 41 | 89 | Work In Progress | Not Certified | 
| 6 | Ghazipur | Deokali | Raispur | 472450 | Shankarpur | 47 | 42 | 89 | Work In Progress | Not Certified |