Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20086425 | BURANPUR W/S SCHEME (HFCL) | 255.28 | 131.78 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | Yes | 0 | NA | No | 16095.00 | 16044.20 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Manihari | Buran Pur | 471758 | Buranpur | 119 | 104 | 87 | Work In Progress | Not Certified |
| 2 | Ghazipur | Manihari | Buran Pur | 471759 | Faridpur Hulas Rai | 41 | 35 | 85 | Work In Progress | Not Certified |
| 3 | Ghazipur | Manihari | Buran Pur | 471760 | Dhava M. Faridpur | 57 | 50 | 88 | Work In Progress | Not Certified |
| 4 | Ghazipur | Manihari | Buran Pur | 471761 | Jolhata | 71 | 63 | 89 | Work In Progress | Not Certified |