Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20086466 | MOHABBAT PUR W/S SCHEME (HFCL) | 258.36 | 122.48 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Manihari | Mohabbat Pur | 471785 | Mohabbat Pur | 405 | 396 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Manihari | Mohabbat Pur | 471786 | A.ma. Mohabbatpur | 6 | 5 | 83 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Manihari | Mohabbat Pur | 471787 | Baghipur | 2 | 2 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ghazipur | Manihari | Mohabbat Pur | 471788 | Naseerabad | 3 | 2 | 67 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Manihari | Mohabbat Pur | 471789 | Veersingh | 6 | 5 | 83 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | NA | 8 | NA | No | 15676.00 | 15311.00 |