Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20086541 | PAIKAULIYA & PAIKOLIYA MUSLIM GP wss | 395.86 | 129.42 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 31 | 31 | Yes | 0 | NA | No | 14844.00 | 14844.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Gaur | Paikauliya | 449328 | Paikauliya | 318 | 318 | 100 | Har Gar Jal | Not Certified |
| 2 | Basti | Gaur | Paikoliya | 449580 | Paikoliya | 284 | 283 | 100 | Work In Progress | Not Certified |
| 3 | Basti | Gaur | Paikoliya | 449581 | Budhiya | 75 | 74 | 99 | Work In Progress | Not Certified |