Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20086551 | SHAKAR DAHA GP wss | 215.83 | 97.99 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 17 | 17 | Yes | 0 | NA | No | 10878.00 | 10000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Harraiya | Shakar Daha | 449634 | Shakar Daha | 161 | 159 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Harraiya | Shakar Daha | 449635 | Matihaniya | 60 | 59 | 98 | Work In Progress | Not Certified |
| 3 | Basti | Harraiya | Shakar Daha | 449636 | Ubxya Gangaram | 58 | 57 | 98 | Work In Progress | Not Certified |
| 4 | Basti | Harraiya | Shakar Daha | 449637 | Dughra Bodhi | 38 | 37 | 97 | Work In Progress | Not Certified |
| 5 | Basti | Harraiya | Karamdar | 449809 | Pikaura Misir | 42 | 41 | 98 | Work In Progress | Not Certified |