Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20086569
SCHEME NAME
SHEKHPUR & NEVARAHA VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
446.96
EXPENDITURE
282.91
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
31115.00
Meter
Length Laid
21132.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Sujanganj | Shekhapur | 469272 | Ramnagara | 50 | 46 | 92% | Work In Progress | Not Certified |
| 2 | Jaunpur | Sujanganj | Shekhapur | 469273 | Girahuli | 85 | 80 | 94% | Work In Progress | Not Certified |
| 3 | Jaunpur | Sujanganj | Shekhapur | 469274 | Shekhapur | 67 | 62 | 93% | Work In Progress | Not Certified |
| 4 | Jaunpur | Sujanganj | Shekhapur | 469275 | Ahiladpur | 66 | 56 | 85% | Work In Progress | Not Certified |
| 5 | Jaunpur | Sujanganj | Shekhapur | 469276 | Daudpur | 98 | 93 | 95% | Work In Progress | Not Certified |
| 6 | Jaunpur | Sujanganj | Nevaraha | 469277 | Nevaraha | 103 | 103 | 100% | Har Ghar Jal | Not Certified |
| 7 | Jaunpur | Sujanganj | Nevaraha | 469278 | Sakapur | 128 | 117 | 91% | Work In Progress | Not Certified |