Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20086572 | AHAMADPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 263.18 | 79.15 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 16 | NA | No | 12007.00 | 10245.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mariyahun | Ahamadpur | 469806 | Gadaiya | 57 | 21 | 37 | Work In Progress | Not Certified |
| 2 | Jaunpur | Mariyahun | Ahamadpur | 469807 | Chaharpur | 117 | 69 | 59 | Work In Progress | Not Certified |
| 3 | Jaunpur | Mariyahun | Ahamadpur | 469808 | Ahamadpur | 101 | 79 | 78 | Work In Progress | Not Certified |
| 4 | Jaunpur | Mariyahun | Ahamadpur | 469809 | Jamin Jangi | 2 | 1 | 50 | Work In Progress | Not Certified |