Scheme Details
DISTRICT
Maharajganj
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20086709
SCHEME NAME
Pipria GP Water Supply Scheme
ESTIMATED COST
164.22
EXPENDITURE
79.47
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4979.00
Meter
Length Laid
5410.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Nichlaul | Pipiriya | 453667 | Pipariya | 175 | 175 | 100% | Har Ghar Jal | Not Certified |