Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20086718 | Barai_Dallipur W/S scheme | 405.86 | 173.78 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 24888.00 | 24861.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | BADAGAON | DALLIPUR | 475542 | FATEPUR | 114 | 109 | 96 | Work In Progress | Not Certified | 
| 2 | Varanasi | BADAGAON | DALLIPUR | 475543 | DALLIPUR | 236 | 223 | 94 | Work In Progress | Not Certified | 
| 3 | Varanasi | BADAGAON | BARAI | 475594 | BIKAPUR | 159 | 153 | 96 | Work In Progress | Not Certified | 
| 4 | Varanasi | BADAGAON | BARAI | 475595 | CHAK BARAI | 4 | 4 | 100 | Har Gar Jal | Not Certified | 
| 5 | Varanasi | BADAGAON | BARAI | 475596 | BARAI | 218 | 211 | 97 | Work In Progress | Not Certified |