Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20086811 | NATHMALPUR HETHARIYA WSS | 467.60 | 286.56 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 23795.00 | 23795.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Jahangirganj | Faridpur Hethariya | 438028 | Faridpur Hethariya | 144 | 140 | 97 | Work In Progress | Not Certified | 
| 2 | Ambedkar Nagar | Jahangirganj | Shankarpur Warji | 438029 | Shankarpur Warji | 67 | 60 | 90 | Work In Progress | Not Certified | 
| 3 | Ambedkar Nagar | Jahangirganj | Shankarpur Warji | 438030 | Allipur Warji | 109 | 107 | 98 | Work In Progress | Not Certified | 
| 4 | Ambedkar Nagar | Jahangirganj | KASTURIPUR | 438031 | Kasturipur | 80 | 78 | 98 | Work In Progress | Not Certified | 
| 5 | Ambedkar Nagar | Jahangirganj | KASTURIPUR | 438154 | DANDWA DEVRAM | 310 | 308 | 99 | Work In Progress | Not Certified | 
| 6 | Ambedkar Nagar | Jahangirganj | Faridpur Hethariya | 677494 | NATHMALPUR HETHARIYA | 84 | 82 | 98 | Work In Progress | Not Certified |