Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20086918 | Rajpur W/S Scheme | 261.15 | 119.39 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 15150.00 | 14908.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Arajiline | Raj Pur | 476438 | Raj Pur | 117 | 115 | 98 | Work In Progress | Not Certified |
| 2 | Varanasi | Arajiline | Raj Pur | 476439 | Bibhori | 56 | 51 | 91 | Work In Progress | Not Certified |
| 3 | Varanasi | Arajiline | Raj Pur | 476440 | Dodahi | 15 | 6 | 40 | Work In Progress | Not Certified |
| 4 | Varanasi | Arajiline | Raj Pur | 476441 | Bansipur | 179 | 177 | 99 | Work In Progress | Not Certified |