| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20086995 | BABHANPURA WSS | 569.32 | 341.67 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 34739.00 | 32440.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Jahangirganj | Babhanpura | 438054 | Babhanpura | 142 | 138 | 97 | Work In Progress | Not Certified | 
| 2 | Ambedkar Nagar | Jahangirganj | Babhanpura | 438055 | Semra Tappa Haveli | 71 | 71 | 100 | Har Gar Jal | Not Certified | 
| 3 | Ambedkar Nagar | Jahangirganj | Gadhwal | 438057 | Gadhwal | 266 | 266 | 100 | Har Gar Jal | Not Certified | 
| 4 | Ambedkar Nagar | Jahangirganj | Saray Hankar | 438238 | Saray Hankar | 101 | 97 | 96 | Work In Progress | Not Certified | 
| 5 | Ambedkar Nagar | Jahangirganj | Saray Hankar | 438239 | Kathmorwa | 136 | 134 | 99 | Work In Progress | Not Certified |