Scheme Details
DISTRICT
Ghazipur
AGENCY
VSA
SCHEME ID
20087036
SCHEME NAME
GAUSPUR BUJURGA REORGANISATION W/S SCHEME (VSA)
ESTIMATED COST
1352.34
EXPENDITURE
510.78
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
9
T/W Progress
Required
8
Boring Done
8
Air Compressor Done
8
O.P. Unit Done
8
OHT Progress
Required
5
Work Started
0
Work Completed
0
Solar Plant
Required
108
Procured
108
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
57680.00
Meter
Length Laid
56568.00
Meter
Scheme Assigned Villages
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Manihari | Gauspur | 471686 | Gauspur | 706 | 700 | 99% | Work In Progress | Not Certified |
| 2 | Ghazipur | Manihari | Buzurga | 471753 | Buzurga | 268 | 259 | 97% | Work In Progress | Not Certified |
| 3 | Ghazipur | Manihari | Buzurga | 471754 | Salempur | 100 | 94 | 94% | Work In Progress | Not Certified |
| 4 | Ghazipur | Manihari | Buzurga | 471755 | Yakubpur | 39 | 34 | 87% | Work In Progress | Not Certified |
| 5 | Ghazipur | Manihari | Buzurga | 471756 | Chak Sikandar | 52 | 48 | 92% | Work In Progress | Not Certified |
| 6 | Ghazipur | Manihari | Takipur | 471757 | Takki Pur | 144 | 131 | 91% | Work In Progress | Not Certified |
| 7 | Ghazipur | Manihari | Sarai Gokul | 471817 | Mohanpur Kala | 46 | 45 | 98% | Work In Progress | Not Certified |
| 8 | Ghazipur | Manihari | Goppur | 471818 | Gokalpur | 104 | 91 | 88% | Work In Progress | Not Certified |
| 9 | Ghazipur | Manihari | Hardaspur Kassi | 471839 | Hardaspur Kassi | 226 | 211 | 93% | Work In Progress | Not Certified |