Scheme Details
DISTRICT
Bulandshahr
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20087107
SCHEME NAME
Babiya WSS
ESTIMATED COST
274.06
EXPENDITURE
149.00
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7997.00
Meter
Length Laid
7900.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Sikandrabad | Bavaiya Biswanah | 393141 | Biswanah | 86 | 86 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bulandshahr | Sikandrabad | Bavaiya Biswanah | 393142 | Babiya | 145 | 145 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bulandshahr | Sikandrabad | Bavaiya Biswanah | 393143 | Kherpur Til | 160 | 160 | 100% | Har Ghar Jal | Not Certified |