S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Mainpuri NCC Ltd. 20087114 GANGAPUR MUHANADPUR + SARAI LATIF + ASHOKPUR HARKHATKANI GRAM PANCHAYAT WATER SUPPLY SCHEME 516.27 296.53 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
5 2 2 2 2 1 0 1 10 10 Yes 0 NA No 29366.00 28830.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Mainpuri Kuraoli Saraylatif 400063 Saray Latif 286 266 93 Work In Progress Not Certified
2 Mainpuri Kuraoli Ashokpur Har Khatkani 400076 Uddetpur Har Khatkani 40 36 90 Work In Progress Not Certified
3 Mainpuri Kuraoli Gangapur Muhammadpur 400093 Gangapur Muhamadpur 404 393 97 Work In Progress Not Certified
4 Mainpuri Kuraoli Gangapur Muhammadpur 400094 Gahiyarpur 59 32 54 Work In Progress Not Certified
5 Mainpuri Kuraoli Ashokpur Har Khatkani 400148 Ashokpurhar Khatkani 377 376 100 Work In Progress Not Certified