Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20087125
SCHEME NAME
MARDAPUR_JALALPUR MARDAPUR WATER SUPPLY SCHEME
ESTIMATED COST
405.64
EXPENDITURE
157.96
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
35097.00
Meter
Length Laid
15120.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Saidabad | Jalalpur Mardapur | 433546 | Jalalpur Mardapur | 342 | 309 | 90% | Work In Progress | Not Certified |
| 2 | Prayagraj | Saidabad | Mardapur | 433605 | Mardapur | 448 | 403 | 90% | Work In Progress | Not Certified |