Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Ghazipur VSA 20087167 JALALABAD REORGANISATION W/S SCHEME (VSA) 3238.24 895.59 view more

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
9 14 14 14 14 7 7 1 246 246 NA 0 NA No 146165.00 144548.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Ghazipur Jakhania Jalalabad 471505 Jalalabad 2818 2553 91 Work In Progress Not Certified
2 Ghazipur Jakhania Jalalabad 471506 Shahpur Barik 6 1 17 Work In Progress Not Certified
3 Ghazipur Jakhania Tandwa Tappa Jalalabad 471522 Tandwa Tappa Jalalabad 141 91 65 Work In Progress Not Certified
4 Ghazipur Jakhania Tandwa Tappa Jalalabad 471523 Jasauli 96 71 74 Work In Progress Not Certified
5 Ghazipur Jakhania Tandwa Tappa Jalalabad 471524 Ghanbaur 83 71 86 Work In Progress Not Certified
6 Ghazipur Jakhania Hardaspur Khurd 471632 Hardaspur Khurd 174 126 72 Work In Progress Not Certified
7 Ghazipur Jakhania Hardaspur Khurd 471633 Katauli 159 135 85 Work In Progress Not Certified
8 Ghazipur Virno BADHHOPUR 472565 Badhhopur 575 457 79 Work In Progress Not Certified
9 Ghazipur Virno BADHHOPUR 677906 Rampur Murhar 100 82 82 Work In Progress Not Certified