Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
20087184
SCHEME NAME
Surasana Water Supply Scheme
ESTIMATED COST
250.88
EXPENDITURE
240.50
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
21
Procured
21
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10945.00
Meter
Length Laid
11961.60
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Dalmau | Surasana | 417366 | Surasana | 412 | 412 | 100% | Har Ghar Jal | Not Certified |