Scheme Details
DISTRICT
Azamgarh
AGENCY
GAJA - SGIPL (JV)
SCHEME ID
20087250
SCHEME NAME
UPATAPAR BASGAON & MATHIYA ZAPTI MAPHI WATER SUPPLY SCHEME
ESTIMATED COST
420.15
EXPENDITURE
273.13
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24817.00
Meter
Length Laid
24817.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Atrauliya | Mathiya Japti Mafi | 461055 | Uptaparbasgaown | 256 | 70 | 27% | Work In Progress | Not Certified |
| 2 | Azamgarh | Atrauliya | Mathiya Japti Mafi | 461056 | Mathiya Zapti Maphi | 120 | 118 | 98% | Work In Progress | Not Certified |
| 3 | Azamgarh | Atrauliya | Uptaparbasgaown | 461057 | Zameen Gorthani | 92 | 87 | 95% | Work In Progress | Not Certified |