Scheme Details
DISTRICT Azamgarh
AGENCY GAJA - SGIPL (JV)
SCHEME ID 20087262
SCHEME NAME HARDIYA,ADILPUR WATER SUPPLY SCHEME
ESTIMATED COST 328.94
EXPENDITURE 105.08
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 0
O.P. Unit Done 0
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19666.00 Meter
Length Laid 13500.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Azamgarh Atrauliya Adilpur 461127 Adilpur 166 142 86% Work In Progress Not Certified
2 Azamgarh Atrauliya Hardiya 461128 Bhanipur 54 43 80% Work In Progress Not Certified
3 Azamgarh Atrauliya Hardiya 461129 Ramapur 12 6 50% Work In Progress Not Certified
4 Azamgarh Atrauliya Hardiya 461130 Hardiya 100 90 90% Work In Progress Not Certified