Scheme Details
DISTRICT
Jaunpur
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20087285
SCHEME NAME
Sawain
ESTIMATED COST
538.09
EXPENDITURE
173.74
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
44
Procured
44
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
25044.00
Meter
Length Laid
25044.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Suithkala | Gangauli | 468191 | Gangauli | 264 | 263 | 100% | Work In Progress | Not Certified |
| 2 | Jaunpur | Suithkala | Sawain | 468195 | Sawain | 681 | 664 | 98% | Work In Progress | Not Certified |