Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20087322
SCHEME NAME
CHILAR W/S SCHEME
ESTIMATED COST
238.05
EXPENDITURE
65.22
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
15
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13208.00
Meter
Length Laid
13208.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Chilar | 472332 | Chilar | 486 | 486 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ghazipur | Deokali | Chilar | 472333 | Kripal Chak | 3 | 1 | 33% | Work In Progress | Not Certified |