Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20087333
SCHEME NAME
MURTAJIPUR W/S SCHEME
ESTIMATED COST
214.62
EXPENDITURE
85.84
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
14
Procured
14
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6199.00
Meter
Length Laid
3611.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Bhanwarkol | Murtajipur | 473763 | Murtajipur | 276 | 276 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ghazipur | Bhanwarkol | Murtajipur | 473764 | Chak Wajid Pur | 4 | 1 | 25% | Work In Progress | Not Certified |
| 3 | Ghazipur | Bhanwarkol | Murtajipur | 473767 | Jalalpur Mutwali | 136 | 125 | 92% | Work In Progress | Not Certified |