Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | GA INFRA - BABA (JV) | 20087354 | BHADAR | 232.89 | 106.13 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 10 | NA | No | 10275.00 | 10207.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Airayan | Bhadar | 428433 | Bhadar | 506 | 506 | 100 | Har Gar Jal | Not Certified |
| 2 | Fatehpur | Airayan | Bhadar | 428434 | Kashidaspur Tikari | 142 | 126 | 89 | Work In Progress | Not Certified |