Scheme Details
DISTRICT
Fatehpur
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20087361
SCHEME NAME
SULTANPUR GHOSH
ESTIMATED COST
390.76
EXPENDITURE
221.77
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
15
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18523.00
Meter
Length Laid
17517.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Airayan | Sultanpur Ghosh | 428460 | Sultanpur Ghosh | 747 | 671 | 90% | Work In Progress | Not Certified |
| 2 | Fatehpur | Airayan | Sultanpur Ghosh | 428461 | Paharpur | 86 | 86 | 100% | Har Ghar Jal | Not Certified |
| 3 | Fatehpur | Airayan | Sultanpur Ghosh | 428462 | Ahmadpur | 72 | 68 | 94% | Work In Progress | Not Certified |