Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Larsen & Toubro Ltd | 20087383 | MEHRAUR W/S SCHEME | 222.40 | 144.76 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 10 | NA | No | 15711.00 | 15012.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Kasimabad | MEHRAUR | 473067 | Mehraur | 202 | 200 | 99 | Work In Progress | Not Certified | 
| 2 | Ghazipur | Kasimabad | MEHRAUR | 473068 | Bangalpur | 87 | 85 | 98 | Work In Progress | Not Certified | 
| 3 | Ghazipur | Kasimabad | MEHRAUR | 473069 | Chakasiya | 124 | 122 | 98 | Work In Progress | Not Certified | 
| 4 | Ghazipur | Kasimabad | MEHRAUR | 473070 | Pilkuwa Kusum | 4 | 3 | 75 | Work In Progress | Not Certified | 
| 5 | Ghazipur | Kasimabad | MEHRAUR | 678578 | Pilkuwa Khas | 8 | 1 | 12 | Work In Progress | Not Certified |