Scheme Details
DISTRICT
Bijnor
AGENCY
LC INFRA
SCHEME ID
20087642
SCHEME NAME
Abdullapur Dahana water supply scheme
ESTIMATED COST
170.07
EXPENDITURE
168.73
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5056.00
Meter
Length Laid
5056.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Noorpur | Abdullapur Dahana | 387680 | Abdulla Nagar Dahana | 411 | 411 | 100% | Har Ghar Jal | Certified |