Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20087696
SCHEME NAME
SYAU water supply scheme
ESTIMATED COST
546.92
EXPENDITURE
411.53
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
51
Procured
51
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18275.00
Meter
Length Laid
13466.75
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Jalilpur | Syau | 387365 | Syau | 1403 | 1403 | 100% | Har Ghar Jal | Not Certified |