Scheme Details
DISTRICT
Bijnor
AGENCY
LC INFRA
SCHEME ID
20087868
SCHEME NAME
Aladinpur Kirat Village Water Supply Scheme
ESTIMATED COST
313.02
EXPENDITURE
233.45
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9601.00
Meter
Length Laid
11500.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Alhepur | Dhakka Karam Chand | 387059 | Dhakka Karam Chand | 715 | 715 | 100% | Har Ghar Jal | Certified |
| 2 | Bijnor | Alhepur | Dhakka Karam Chand | 387060 | Aladinpur Kirat | 37 | 37 | 100% | Har Ghar Jal | Certified |