Scheme Details
DISTRICT
Mau
AGENCY
GA INFRA-VPL
SCHEME ID
20088084
SCHEME NAME
BANIYAPAR TAHIR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
392.22
EXPENDITURE
375.34
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
22380.00
Meter
Length Laid
22000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Badraon | Baniyapar Tahir | 465257 | Baniyapar Tahir | 312 | 302 | 97% | Work In Progress | Not Certified |
| 2 | Mau | Badraon | Baniyapar Tahir | 465258 | Banakara Buzurg | 115 | 115 | 100% | Har Ghar Jal | Not Certified |
| 3 | Mau | Badraon | Baniyapar Tahir | 465259 | Dadanpur Atalupur | 97 | 88 | 91% | Work In Progress | Not Certified |