Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20088191
SCHEME NAME
POOTA W/S SCHEME (HFCL)
ESTIMATED COST
239.13
EXPENDITURE
108.15
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12112.00
Meter
Length Laid
9983.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Poota | 472388 | Poota | 349 | 341 | 98% | Work In Progress | Not Certified |