Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20088199 | Harhua Zone 4_Singhapur_Karoma_Ausanp Ur Water Supply Scheme | 767.46 | 337.46 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 8 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 56 | 56 | No | 0 | NA | No | 43706.00 | 23706.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | HARAHUA | KAROMA | 476008 | KAROMA | 307 | 297 | 97 | Work In Progress | Not Certified |
| 2 | Varanasi | HARAHUA | KAROMA | 476009 | GAHARWARPUR | 40 | 39 | 98 | Work In Progress | Not Certified |
| 3 | Varanasi | HARAHUA | AUSANPUR | 476067 | AUSANPUR | 479 | 426 | 89 | Work In Progress | Not Certified |
| 4 | Varanasi | HARAHUA | SINGHAPUR | 476091 | SINGHAPUR | 157 | 131 | 83 | Work In Progress | Not Certified |
| 5 | Varanasi | HARAHUA | SINGHAPUR | 476092 | DHANESHARI | 228 | 224 | 98 | Work In Progress | Not Certified |
| 6 | Varanasi | HARAHUA | SINGHAPUR | 476093 | RAM SINGHPUR | 73 | 55 | 75 | Work In Progress | Not Certified |
| 7 | Varanasi | HARAHUA | SINGHAPUR | 476094 | ANEGPUR | 2 | 2 | 100 | Har Gar Jal | Not Certified |
| 8 | Varanasi | HARAHUA | SINGHAPUR | 476095 | VISHUNPUR | 8 | 2 | 25 | Work In Progress | Not Certified |