Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20088250 | KAITHAWALIA BINDWALIA REORGANISATION W/S SCHEME (VSA) | 944.93 | 238.08 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Ghazipur | Bakshupur | 472897 | Baxupur | 117 | 81 | 69 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Ghazipur | Bakshupur | 472900 | Alampatti | 107 | 82 | 77 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Ghazipur | Bindwalia | 472928 | Bindwalia | 373 | 266 | 71 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Ghazipur | Bindwalia | 472929 | Chak Phazullah | 82 | 61 | 74 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Ghazipur | Bindwalia | 472930 | Bag Nurullah | 29 | 21 | 72 | Work In Progress | Not Certified | Not Verified |
6 | Ghazipur | Ghazipur | Bindwalia | 472931 | Chak Faiz | 53 | 42 | 79 | Work In Progress | Not Certified | Not Verified |
7 | Ghazipur | Ghazipur | Bindwalia | 472932 | Chak Kuresh | 1 | 1 | 100 | Har Gar Jal | Not Certified | Not Verified |
8 | Ghazipur | Ghazipur | Kaithwalia | 472933 | Kaithwalia | 310 | 310 | 100 | Har Gar Jal | Not Certified | Not Verified |
9 | Ghazipur | Ghazipur | Bindwalia | 472934 | Rampur Urf Jhingurpatti | 9 | 9 | 100 | Har Gar Jal | Not Certified | Not Verified |
10 | Ghazipur | Ghazipur | Bindwalia | 472935 | Jamalapur | 4 | 1 | 25 | Work In Progress | Not Certified | Not Verified |
11 | Ghazipur | Ghazipur | Bindwalia | 472936 | Mahuwadpur | 125 | 101 | 81 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
11 | 4 | 4 | 4 | 4 | 3 | 0 | 1 | 60 | 60 | NA | 0 | NA | No | 40467.00 | 40203.00 |