Scheme Details
DISTRICT
Varanasi
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20088283
SCHEME NAME
Jariyari_Mohanidih_Suari Water Supply Scheme
ESTIMATED COST
393.40
EXPENDITURE
220.94
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
38970.00
Meter
Length Laid
38882.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Cholapur | Mohanideeh | 475879 | Mohanidih | 149 | 145 | 97% | Work In Progress | Not Certified |
| 2 | Varanasi | Cholapur | JARIYARI | 475911 | Gopaur 2 | 40 | 37 | 92% | Work In Progress | Not Certified |
| 3 | Varanasi | Cholapur | JARIYARI | 475912 | Varaji | 72 | 53 | 74% | Work In Progress | Not Certified |
| 4 | Varanasi | Cholapur | JARIYARI | 475913 | Jariyari | 339 | 319 | 94% | Work In Progress | Not Certified |
| 5 | Varanasi | Cholapur | JARIYARI | 680730 | Goppur (First) | 203 | 8 | 4% | Work In Progress | Not Certified |