Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20088289
SCHEME NAME
AMWA ASKARAN & SAMPUR LAKAMI W/S SCHEME (HFCL)
ESTIMATED COST
322.46
EXPENDITURE
83.72
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
15
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18860.00
Meter
Length Laid
16860.00
Meter
Scheme Assigned Villages
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Varachavar | AMWA ASKARAN | 473439 | Amwa Askaran | 110 | 107 | 97% | Work In Progress | Not Certified |
| 2 | Ghazipur | Varachavar | AMWA ASKARAN | 473440 | Tiwaripur | 57 | 55 | 96% | Work In Progress | Not Certified |
| 3 | Ghazipur | Varachavar | AMWA ASKARAN | 473441 | Jogipur | 10 | 9 | 90% | Work In Progress | Not Certified |
| 4 | Ghazipur | Varachavar | Sampur Lakami | 473442 | Baki Buzurg | 44 | 42 | 95% | Work In Progress | Not Certified |
| 5 | Ghazipur | Varachavar | Sampur Lakami | 473443 | Salampur Lakami | 112 | 108 | 96% | Work In Progress | Not Certified |
| 6 | Ghazipur | Varachavar | AMWA ASKARAN | 678593 | Ayajpur | 1 | 1 | 100% | Har Ghar Jal | Not Certified |