Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20088307 | BARHI URF BANDAE W/S SCHEME (HFCL) | 254.67 | 83.26 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Varachavar | Barhi Urf Bandae | 473383 | Barhi Urf Bandae | 194 | 181 | 93 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Varachavar | Barhi Urf Bandae | 473384 | Kateysar | 73 | 69 | 95 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Varachavar | Barhi Urf Bandae | 473385 | Mubarakhpur T. Bandae | 40 | 38 | 95 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Varachavar | Barhi Urf Bandae | 678629 | Naserpurchak Dayal T. Bandhae | 16 | 14 | 88 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | Yes | 0 | NA | No | 9427.00 | 11505.00 |