Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20088321 | BHAWANIPUR & JEVAL W/S SCHEME (HFCL) | 365.68 | 109.44 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Deokali | Jeval | 472339 | Jeval | 276 | 264 | 96 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Deokali | Bhawanipur | 472411 | Bhawanipur | 152 | 141 | 93 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Deokali | Bhawanipur | 472412 | Horilpur | 96 | 90 | 94 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Deokali | Bhawanipur | 472413 | Rajadipur | 65 | 62 | 95 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | NA | 15 | NA | No | 25453.00 | 17288.00 |