| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20088352 | BAHARAR W/S SCHEME (HFCL) | 226.77 | 70.00 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | NA | 8 | NA | No | 9542.00 | 9294.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Kasimabad | Baharar | 473074 | Baharar | 300 | 276 | 92 | Work In Progress | Not Certified |
| 2 | Ghazipur | Kasimabad | Baharar | 473075 | Berukharha | 116 | 104 | 90 | Work In Progress | Not Certified |
| 3 | Ghazipur | Kasimabad | Baharar | 678589 | Pah Ershanand | 2 | 1 | 50 | Work In Progress | Not Certified |