Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ghazipur
AGENCY HFCL- JWIL (JV)
SCHEME ID 20088418
SCHEME NAME SAWANA W/S SCHEME (HFCL)
ESTIMATED COST 192.85
EXPENDITURE 100.10
AUTOMATION STATUS
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 8
Transformer Procured NA
Work Status No
Distribution Line
Total Length 6559.00 Meter
Length Laid 5961.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ghazipur Kasimabad Sawana 473274 Sawana 160 157 98% Work In Progress Not Certified
2 Ghazipur Kasimabad Sawana 473275 Chilbili 112 111 99% Work In Progress Not Certified
3 Ghazipur Kasimabad Sawana 473276 Mohammadpur M.sagapali Dayal S 84 83 99% Work In Progress Not Certified