Scheme Details
DISTRICT
Aligarh
AGENCY
PNC-SPML-JV
SCHEME ID
20088468
SCHEME NAME
NAYELA & VAJIDPUR WSS
ESTIMATED COST
299.40
EXPENDITURE
138.42
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10239.00
Meter
Length Laid
10000.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Khair | Nayela | 394344 | Nayela | 144 | 139 | 97% | Work In Progress | Not Certified |
| 2 | Aligarh | Khair | Nayela | 394345 | Bhanera | 111 | 109 | 98% | Work In Progress | Not Certified |
| 3 | Aligarh | Khair | Vajidpur | 394360 | Vajidpur | 244 | 233 | 95% | Work In Progress | Not Certified |