Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20088474 | HAZIPUR W/S SCHEME (HFCL) | 235.22 | 94.23 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | NA | 0 | NA | No | 7863.00 | 8285.82 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Sadat | Hazipur | 471995 | Hazipur | 141 | 126 | 89 | Work In Progress | Not Certified |
| 2 | Ghazipur | Sadat | Hazipur | 471996 | Madhotanda | 77 | 71 | 92 | Work In Progress | Not Certified |
| 3 | Ghazipur | Sadat | Hazipur | 471997 | Chak Beni Raipur | 79 | 71 | 90 | Work In Progress | Not Certified |