Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 20088559 | ATANPUR WATER SUPPLY SCHEME | 321.09 | 119.98 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 28 | 28 | Yes | 0 | NA | No | 26348.00 | 26348.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Bahariya | Atanpur | 432090 | Atanpur | 347 | 315 | 91 | Work In Progress | Not Certified | 
| 2 | Prayagraj | Bahariya | Atanpur | 432091 | Sultanpur | 94 | 76 | 81 | Work In Progress | Not Certified | 
| 3 | Prayagraj | Bahariya | Atanpur | 432092 | Chak Yarmohammad Urf Rampur | 58 | 46 | 79 | Work In Progress | Not Certified |